Projects are progressing perfectly and within schedules

Autopsy of the projects carried out by the services of the Ministry of Culture in the historical core of the former royal estate of thegeneral budget 58,000,000 eurosheld by the Minister of Culture Lina Mendoni, head of a multi-member echelon in the Ministry of Culture.

Maintenance of Palace items

Lina Mendoni is well informed about the progress of the projects and gives clear instructions for their continuation, so that the overall project of restoration, promotion and creation of the land is completed in the best way and within predetermined schedules.

Archikipourou’s house before and after the restoration work

As stated by Lina Mendoni: “In the context of the regular autopsies we have conducted in the former royal estate of Tatoi, we have carefully reviewed the progress of the ongoing projects and given instructions for faithfully following their completion schedules. We have seen the restoration projects that have been completed, those that are ongoing, but also need to be accelerated so as not to deviate from their completion schedule. monument, while we found a satisfactory rate of recording, documentation and maintenance of the various collections of the land. The year 2025 is the milestone for the restoration works of the historical core of Tatoi, because at the end of it the basic museum infrastructures have been completed and given to the public. The restoration, promotion and operation of the land is a symbolic project in the context of the overall development planning of the government and the Ministry of Culture”.

View from inside the new Voustasiou, second floor

Work is progressing smoothly on the restoration projects of the Palace, the construction of infrastructure networks and the formation of its environment. At the same time, museological studies have been completed and museographic studies are progressing.

Furniture maintenance work

The progress of the works on the Palace is also followed by the works for the restoration of the Gardens, where a contractor has just been installed, with a completion date of the end of 2025. The Minister of Culture gave instructions to immediately prepare the restoration studies of the greenhouse and the adjacent tennis court, so that it will be ready by the end of next year.

The timetable for the completion of the Neo Voustasiou building restoration project is the same. One of its wings is intended for a Museum of vehicles – memorabilia of the royal family, while the other is a museum dedicated to the agricultural and livestock production of the land. The relevant museological studies have been completed. At the same time, the floor of Neos Voustasiou has been transformed into a conference and event space.

Works inside the Palace

After the restoration of Old Voustasi, the Royal Carriage Museum will be housed there. Important technical issues that arose during the implementation of the project forced the extension of the period of the works, which, however, are now progressing smoothly. And the museological and museographic study of Paleo Voustasio has been completed.

Restoration works on the buildings of the “Parking” complex have been completed and are expected to be handed over for use next fall.

Visitable maintenance laboratories will be located in specific buildings, so that the visitor can follow the process of restoring objects from the collections of the land. One of them will be given to the Scouts, who are currently in Katsimidi, and the second will place a Fire Station, which is absolutely necessary to exist in Tatoi.

Next fall, the finished buildings of the Sturm House, the Carer’s House, the Archikipourou House and the Telecommunications will be handed over for cultural use. The Kitchen building is complete, which from the beginning of 2026, will house the ticket office of the palaces, the cloakroom, the refreshment room and the office of the people in charge of the Palace museum.

Until then, it will temporarily host an exhibition, with all the studies and projects carried out in the historical core of the Tatoi estate, next to the Forester’s House, which is already functioning as an Information Center.

For the three buildings, the Shelter, which will act as an Estate Administration Office, the Pigsty, which will serve as a Souvenir Shop, and the Seasonal Workers Building, which will act as a Small-Scale Training and Cooperation Area with Universities, their restoration Studies have been completed and their inclusion in a financial program is expected.